on the garden level, more HVAC work continued in the family room. vertical ducts were put into place on the north and the south walls and overhead between the beams in the ceiling. the crew also began to work on the bathroom's ceiling exhaust fan which had to be vented outside by snaking its way behind the two closets and existing cabinetry on the kitchen's south wall and then out thorough the family room ceiling.
the HVAC overhaul continued in the cellar too. the ducts that had concerned hubby in late december because they were hanging lower than expected were relocated just slightly and now fit between the ceiling beams. more ducts were placed in the ceiling and along the south wall in both the rear room and the southwest corner of the cellar.
during the week, we coordinated with anastasia to decide upon the location of the electrical panel (southeast corner of the family room opposite the exterior door) and flat screen tv (centered on the family room's north wall). mike and anastasia also recommended adding 4 new floor outlets in the rear room of the parlor floor so that we could eliminate the existing, illegal baseboard outlets already in place. since the family room ceiling below is open, it should be relatively easy to do. we also decided to replace the existing exterior kitchen window.
lastly, after consulting with the plumber, mike recommended that installing a sump pump in the cellar should alleviate the flooding issue as it is designed to turn on when water collects in the pump pit, so we agreed to move in that direction.